Concrete Calculator

Estimate the cubic yards or cubic meters of concrete and the number of 40, 60 or 80 lb bags for a slab, footing or round column, with a waste allowance.

How it works

Choose a slab or footing (length × width × thickness) or a round column or post hole (diameter × height). The concrete calculator gives the volume with waste and the number of premixed bags, or the cubic yards to order from a truck.

Slab: V = L × W × t

Column: V = π d² h ÷ 4

Order = V × (1 + waste)

Bags = order ÷ yield per bag

SymbolMeaningUnit
L, W, tLength, width and thickness of the slab or footingft, in
d, hDiameter and depth of a round column or post holeft, in
wasteAllowance for spillage, uneven subgrade and over-excavation (5 to 10 percent)%
yieldVolume of one bag: 0.30 ft³ (40 lb), 0.375 ft³ (50 lb), 0.45 ft³ (60 lb), 0.60 ft³ (80 lb)ft³

Bag yields are the typical values printed on premixed bags (80 lb makes about 0.60 ft³, 60 lb about 0.45 ft³, 40 lb about 0.30 ft³); check your product. Order by the truck load when you need more than about 1 cubic yard (a ready-mix truck usually has a minimum of 1 to 4 yd³). Common thicknesses: 4 in for a patio or sidewalk slab, 4 to 6 in for a garage floor, footings sized by the building code. A cubic yard of concrete weighs about 4,000 lb (2,400 kg per m³).

Related: Gravel Calculator (for the base), Square Footage Calculator.

Worked example

A 10 ft × 10 ft slab 4 in thick: V = 10 × 10 × 0.3333 = 33.3 ft³ = 1.23 yd³. With 10 percent waste: 1.36 yd³ (1.04 m³) to order, or 62 bags of 80 lb (82 of 60 lb), weighing about 2.7 short tons.

A post hole 12 in across and 36 in deep needs π × 1² ÷ 4 × 3 = 2.36 ft³, about 4 bags of 80 lb.

Things to know

Always add waste: the subgrade is never perfectly flat, forms bow, and some is lost. Order a little extra rather than being short, because a cold joint between two pours is a weakness.

Hand-mixing more than about 20 bags is hard work; for a large slab use a ready-mix truck and have a helper.

The concrete strength, reinforcement, control joints and the base preparation matter as much as the volume. Check local code for footing sizes.

Another worked example: deck footings

A deck needs 12 round footings, each poured in a 10 in form tube 42 in deep. One footing is π ÷ 4 × (10 ÷ 12)² × 3.5 = 1.91 ft³, so twelve need 22.9 ft³ (0.85 yd³).

With 10 percent waste the order is 25.2 ft³. At 0.60 ft³ per 80 lb bag that is 42.0, so buy 42 bags. That is about 3,360 lb to carry and mix, which is still practical with a rented mixer but is close to the point where a small ready-mix delivery is worth pricing.

Bags needed for a 4 inch slab

Exact volume with no waste added, using the typical yields of 0.60 ft³ (80 lb bag) and 0.45 ft³ (60 lb bag).

Slab sizeVolumeCubic yards80 lb bags60 lb bags
4 × 4 ft5.3 ft³0.20 yd³912
6 × 6 ft12.0 ft³0.44 yd³2027
8 × 8 ft21.3 ft³0.79 yd³3648
10 × 10 ft33.3 ft³1.23 yd³5675
10 × 12 ft40.0 ft³1.48 yd³6789
12 × 12 ft48.0 ft³1.78 yd³80107

Add 5 to 10 percent for waste. A 6 in slab needs 1.5 times these amounts.

Common mistakes

  • Leaving the thickness in inches. A 4 in slab is 0.333 ft thick. Multiplying by 4 gives twelve times too much.
  • Using the diameter as the radius for a round footing. The area is π d² ÷ 4, or π r² with r equal to half the diameter.
  • Ordering the exact volume. Running out mid-pour leaves a cold joint. A little left over is far cheaper than being short.
  • Adding too much water. Soupy concrete is easy to place but weaker and more likely to crack. Use the amount on the bag.

Common questions

How do you calculate how much concrete you need?

Volume = length × width × thickness in the same units; divide cubic feet by 27 to get cubic yards. Add 5 to 10 percent for waste.

How many 80 lb bags of concrete make a yard?

About 45 bags (27 ft³ ÷ 0.60 ft³ per bag).

How thick should a concrete slab be?

4 inches for patios, walks and driveways for cars; 5 to 6 inches for heavy loads and garage floors.

How much does a yard of concrete weigh?

About 4,000 lb (1,800 kg), or 2,400 kg per cubic meter.

When should I order ready-mix instead of bags?

Above about 1 cubic yard (45 bags of 80 lb) a truck is usually easier, and for slabs it gives one continuous pour. Suppliers often charge a short-load fee below a minimum quantity, so ask before deciding.

How long does concrete take to cure?

As a general guide: light foot traffic after 24 to 48 hours, vehicles after about 7 days, and the design strength at 28 days. Cold weather slows this. Keep new concrete damp for the first several days for the best strength.

How many cubic feet are in a cubic yard of concrete?

27 cubic feet (3 ft × 3 ft × 3 ft). One cubic yard is 0.765 cubic meters.

Sources

  • American Concrete Institute (ACI 302.1R): guide to concrete floor and slab construction.
  • Typical bag yields from premix manufacturers (Quikrete, Sakrete).

Last reviewed: November 10, 2026

Published by Nick Peterson, mechanical engineer.